Phase 2 Construction Two Week Look Ahead
2 Week Look Ahead


Please click on the Traffic Information link to the left to learn more about possible lane/road closures and alternate routes.


Week of April 24:

Utility Work:

  • President St between Bee St and Spring St.


 
Stormwater Infrastructure Installation:

  • On Spring St between Norman St and Lockwood Blvd. This will be nighttime work from 9PM until 6AM.
  • At the intersection of President St and Cannon St.  The intersection will be closed 24 hours a day for approximately 1 month while the work is completed.  Detour routes will be marked. 

 
 
Other Work:

  • Installation of sidewalk, granite curb, electrical conduit, and landscape irrigation along Cannon St from Lockwood Blvd to US17 North.
  • Installation of sidewalk, granite curb, electrical conduit, and landscape irrigation along Spring St from President St to Lockwood Blvd.

 
 
Week of May 1
:

Utility Work:

  • President St between Bee St and Spring St.

 

Stormwater Infrastructure Installation:

  • On Spring St between Norman St and Lockwood Blvd. This will be nighttime work from 9PM until 6AM.
  • At the intersection of President St and Cannon St.  The intersection will be closed 24 hours a day for approximately 1 month while the work is completed.  Detour routes will be marked. 

 
 
Other Work:

  • Installation of sidewalk, granite curb, electrical conduit, and landscape irrigation along the ramp from Lockwood Blvd to US17 North.
  • Installation of granite curb, electrical conduit, and landscape irrigation along Spring St from President St to Lockwood Blvd.