Help Center
Click to Home
Go To Search
Construction Sequencing


Division III of the Market Street Drainage Improvement Project, Surface Collection & Conveyance and Streetscaping, is expected to begin sometime in 2018.  Although we do not have construction sequencing details at this point in time, it is expected that the vortex boxes in between the Market sheds will be constructed first (one at a time).  Once each of those are completed, the surface conveyance and collection system and streetscaping will be installed block by block, one side of the street at a time, to provide as little disruption to the businesses on Market Street as practical while still allowing the project to be constructed in a reasonable amount of time.  Each section will be demoed, installed, and restored before moving to the next section.  It is anticipated that the construction will last about 36 months.  
Steven A. Kirk, P.E.
Senior Engineering Project Manager
Email

2 George Street
Suite 2100
Charleston, SC 29401

Ph: 843-579-7682
Fx: 843-973-7261