Project Progress

Phase 1 of the proposed drainage improvements were completed in 2018. 

Phase 2 was initially designed and nearly fully permitted in 2019. This original design consisted of complex drainage structures designed to avoid conflict with some of AT&T’s major duct banks under Playground Road. However, due to ongoing and extensive coordination with AT&T, and AT&T’s decision to relocate their utilities along Playground Road, the proposed drainage improvements were redesigned accordingly. The redesign of Phase 2 is complete and is in the permitting process. Phase 2 is expected to begin construction in October 2021, immediately following the conclusion of the AT&T utility relocation work. 

Screenshot (14)